Question asked
- What information does Icon Water provide developers to enable developers to complete design works including detailed metrics.
- What level of accuracy is this information provided to.
- Is this level of accuracy communicated to developers.
- Does Icon Water compensate the builder if the information provided by Icon Water to a developer to complete design works is incorrect (and outside the communicated bounds of accuracy), and the developer incurs additional costs and/or delays.
- Can the Minister detail any instances, in the last five years, where the information provided by Icon Water for developer design works was incorrect, the impact on the developer and whether any compensation was paid.
Answer
Answer Published
24 June 2025
Answered by
Minister for Finance
Answer
Please see attached PDF for a copy of the answer to question on notice No. 288.