Question
Number
622
Subject
ActewAGL
(Energy network maintenance)
(Energy network maintenance)
Asked by
Milligan, James
Directed to
Minister for Finance
Question asked on
17 September 2025
Answer due on
19 October 2025
Question asked
- Who is responsible for the maintenance of the energy network in the ACT.
- How is the maintenance of the energy network financed.
- How many components of the energy network are within 3 years of the end of their life and what are these components.
- How does the ACT Government plan to replace or renew the components referred to in part (3).
- Does the ACT Government have a comprehensive energy network infrastructure plan which encompasses Evoenergy, other private and ACT Government owned assets.
Answer
Answer Published
21 October 2025
Answered by
Minister for Finance
Answer
QON—Please see attached PDF for a copy of the answer to question on notice No 622.
Attachments