(Holt Oval Rehabilitation Cost)
Asked by
Kikkert, Elizabeth
Directed to
Minister for Sport and Recreation
Question asked on
26 October 2023
Answer due on
27 November 2023
Question asked
  1. What was the total cost of the rehabilitation of the Holt ovals along Moyes Crescent.
  2. Can the Minister provide an itemised list of the costs referred to in part (1).

Answer

Answer Published
22 November 2023
Answered by
Minister for Sport and Recreation
Answer
  1. The total cost of the rehabilitation of the Holt ovals along Moyes Crescent was $3,187,000.00.
  2. Itemised costing is provided in the table below: 

Project Delivery Overheads (MPC fees, insurance, training levy, project management)

$717,855.57

Total project construction costs

$2,469,144.43

Comprising: 

Preliminaries  

$100,860.01

Civil earthworks

$737,254.96

Irrigation/meter pits   

$295,040.85

Playing surface/turf    

$658,687.50

Sportsground floodlighting

$287,318.54

Landscaping

$106,639.56

New pavilion

$262,517.80

Miscellaneous

$20,825.21