Question - Planning

Question

Number
2120
Subject
Planning
(Ginninderry)
Asked by
Cain, Peter
Directed to
Minister for Housing and Suburban Development
Question asked on
28 August 2024
Answer due on
30 September 2024
Question asked
  1. What is the total cost of the urban development of Ginninderry up to 2023-24.
  2. What is the breakdown of the primary cost areas, i.e. road infrastructure, utilities infrastructure, of the total cost.
  3. What is the cost of the urban development of Ginninderry each year since commencement up to 2023-24.

Answer

Answer Published
21 October 2024
Answered by
Minister for Housing and Suburban Development
Answer

(1) The total cost of the urban development of Ginninderry up to 2023-24 is $304.5m.

(2) The breakdown of the primary cost areas as tracked by the Suburban Land Agency and Ginninderry Joint Venture is shown in the table below:

Primary Project Cost Areas

Amount ($m)

Project Wide Costs

. Project establishment costs

. Off-site infrastructure works

. Consultant fees for whole of project works

. Environmental clearance zones and land acquisitions

77.8

Neighbourhood Costs

. Neighbourhood landscaping works

. Consultants related to neighbourhood design and approvals

44.0

Stage Costs

. Infrastructure and servicing costs for individual stages

113.1

Overheads

. Management and administration*

69.5

Total

304.5

*overheads as reported by the Ginninderry Joint Venture including project staffing. These costs are not comparable to Suburban Land Agency delivered projects due to the project delivery structure.

(3) The cost of the urban development of Ginninderry each year since commencement of to 2023-24 is shown in the table below:

Financial Year

Amount ($m)

2016-17

30.2

2017-18

13.1

2018-19

39.7

2019-20

47.4

2020-21

39.9

2021-22

37.5

2022-23

47.8

2023-24

48.9

Total

304.5